Subsidy SetuMSME subsidy and compliance
RERA

RERA Exemptions in Haryana: Which Projects Do Not Need Registration

The three cases in which the Act does not require a project to be registered, how the 500 sq m and eight-apartment limits are worded, and why an occupation certificate is not an exemption in Haryana.

Subsidy Setu Editorial Team 6 min read
In this article
  1. Key facts
  2. What is the starting rule?
  3. When is a small project exempt?
  4. When is a completed project exempt?
  5. Is renovation or repair exempt?
  6. Is an occupation certificate an exemption in Haryana?
  7. What about ongoing projects and other kinds of project?
  8. What should I write down before relying on an exemption?
  9. How can our expert team help?

Section 3(2) of the Act exempts three kinds of project from registration: where the land proposed to be developed does not exceed 500 square metres or the apartments proposed do not exceed eight, inclusive of all phases; where the completion certificate was received before the Act commenced; and renovation, repair or re-development with no marketing, selling or new allotment. No lower limit was found in the Haryana Rules. In Haryana an occupation or part-completion certificate is not an exemption: HRERA Panchkula keeps such areas registered until the completion certificate.

Sources checked: 20 October 2026

Facts checked on 20 October 2026 against section 3 of the Real Estate (Regulation and Development) Act, 2016 and the Haryana Real Estate (Regulation and Development) Rules, 2017 as hosted on haryanarera.gov.in, HRERA Panchkula's resolution of 6 August 2025 and the Town and Country Planning Department notification of December 2017.

Key facts

Point What applies Source
Size exemption land not exceeding 500 square metres, or apartments not exceeding eight, inclusive of all phases Act s.3(2)(a)
Completed projects completion certificate received before the Act commenced Act s.3(2)(b)
Renovation renovation, repair or re-development with no marketing, advertising, selling or new allotment Act s.3(2)(c)
Phases each phase is a stand-alone project for registration Act s.3, Explanation
Haryana lower limit none found in the Haryana Rules Haryana Rules 2017
Occupation certificate not an exemption; such areas stay registered until the completion certificate (HRERA Panchkula) Resolution of 06.08.2025

This is general information, not legal advice. Whether your project is exempt depends on its facts.

What is the starting rule?

Section 3(1) says that no promoter may advertise, market, book, sell or offer for sale, or invite people to buy, any plot, apartment or building in a real estate project without registering the project with the Authority first. Section 3(2) then lists what is left out. Relying on an exemption that does not apply is costly, because the registration duty comes before any advertising or booking.

When is a small project exempt?

Section 3(2)(a) says registration is not required "where the area of land proposed to be developed does not exceed five hundred square meters or the number of apartments proposed to be developed does not exceed eight inclusive of all phases".

Read the sentence slowly, because three points follow from it.

The two limits are joined by "or". One limit is about land area and the other about the number of apartments. A plotted colony has no apartments to count, and a project can be under one limit and well above the other. If your project is close to either limit, read the section in the official text linked with this guide and take advice before you rely on it.

The limits are inclusive. A project of exactly 500 square metres, or with exactly eight apartments, does not exceed the limit. A project of 501 square metres, or with nine apartments, does.

All phases count together. The words "inclusive of all phases" mean a development cannot be divided into small phases to stay under the line. At the same time, the Explanation to section 3 says that each phase is to be treated as a stand-alone real estate project, and the promoter registers each phase separately. So the size test looks at the whole development, while each phase is registered on its own.

The Act also lets the appropriate Government lower the threshold below 500 square metres or eight apartments. No lower limit was found in the Haryana Rules. Our free "Do I need RERA registration?" tool applies the limits to your numbers, counts the other phases and tells you when to ask instead of guessing.

When is a completed project exempt?

Section 3(2)(b) says registration is not required where the promoter received a completion certificate for the real estate project before the Act commenced. The test is a completion certificate, and the date it was received. A project that was nearly finished when the Act came into force, but had no completion certificate, does not fall within this exemption.

Is renovation or repair exempt?

Section 3(2)(c) says registration is not required for renovation, repair or re-development which does not involve marketing, advertising, selling or new allotment of any apartment, plot or building. The exemption depends on what is being done, and on what is not being done. If the work comes with marketing, or with selling or allotting new units, the exemption does not apply.

Is an occupation certificate an exemption in Haryana?

No. Promoters often ask about projects that already have an occupation certificate or a part-completion certificate. The Act does not list that as an exemption. HRERA Panchkula recorded in a resolution of 6 August 2025 that areas where an occupation certificate or part-completion certificate has been granted stay registered until the completion certificate is granted. Panchkula covers Hisar, Hansi, Uklana, Fatehabad, Sirsa, Bhiwani, Jind and the rest of Haryana outside Gurugram district.

What about ongoing projects and other kinds of project?

The Haryana Rules have separate provisions for ongoing projects, such as the deposit into the separate account (see our guide to the 70% account). Those provisions set duties for a project; they are not an exemption from registration.

The list in section 3(2) is the list of exemptions in the Act. If someone tells you that a particular scheme or kind of colony is exempt, ask for the provision in writing and check it against the Act and the Rules before you advertise or book a single plot.

What should I write down before relying on an exemption?

  1. the total land area of the development, counting all phases;
  2. the total number of apartments across all phases;
  3. whether any completion certificate was received, and the date;
  4. what is actually being done, if you rely on renovation, repair or re-development, and whether any marketing or allotment is involved;
  5. the authority that covers the project's district: HRERA Gurugram for Gurugram district, HRERA Panchkula for the rest of Haryana.

If the answers are not clear, the cost of asking is small compared with the cost of selling in an unregistered project. Our guide to project registration explains the process once you know you need it.

How can our expert team help?

We check your project against the Act and the Haryana Rules with you, and where it needs registration we prepare the paperwork and keep a checklist of what is pending. Our registration help page describes the support. There is no price list because every project is different, so ask our expert team for a quote and we will reply once we understand your project.

Need help with this? Ask our expert team

Leave your name and mobile number. Our team calls you back within one working day (Monday to Saturday).

Your details are never sold; they are shared only as our Privacy Policy describes.

Frequently asked questions

What is the size limit below which a RERA project is exempt?

Section 3(2)(a) of the Real Estate (Regulation and Development) Act, 2016 says registration is not required where the area of land proposed to be developed does not exceed 500 square metres or the number of apartments proposed to be developed does not exceed eight, inclusive of all phases.

Does each phase of a project count separately for the exemption?

The size limits are counted inclusive of all phases. Separately, the Explanation to section 3 treats each phase as a stand-alone project, so a project that needs registration registers each phase on its own.

Is a project with an occupation certificate exempt in Haryana?

No. The Act exempts only a project whose completion certificate was received before the Act commenced. HRERA Panchkula recorded in a resolution of 6 August 2025 that areas with an occupation or part-completion certificate stay registered until the completion certificate is granted.

Does Haryana set a lower size limit than the Act?

No lower limit was found in the Haryana Real Estate (Regulation and Development) Rules, 2017, so the Act's limits of 500 square metres or eight apartments apply. The Act allows the appropriate Government to lower the threshold, so check the current position before relying on it.

Is renovation or repair of a building exempt from RERA registration?

Section 3(2)(c) of the Act exempts renovation, repair or re-development that does not involve marketing, advertising, selling or new allotment of any apartment, plot or building. If the work comes with marketing or new sales, the exemption does not apply.

Sources

#rera#exemptions#hrera#haryana#project-registration
Share: WhatsApp LinkedIn X

This article is general information for Indian MSMEs, not advice on your specific case. Scheme terms, tax rates and due dates change; the sources above were checked when the article was written or last updated. Speak to a professional before acting on it.

Not sure which schemes fit your business?

Five short steps about your unit, with your name and phone so we can follow up, and you see your matches across central and State schemes. Free.

Keep reading

Practitioner with something to add? Write for us.