₹50 Lakh automation and rooftop solar upgrade of an existing Haryana unit: subsidy stacking blueprint
A running engineering unit on its existing leased premises adds an automated production line and plans a rooftop solar plant. Only the new plant and machinery enters this estimate; the solar plant is kept out of the capital-subsidy base because the policy excludes captive renewable energy plants from eligible capital expenditure and gives them a scheme of their own.
Estimated total: ₹13,97,500 (Core area) to ₹28,54,500 (Prime / Focus area), computed by our subsidy calculator from the notified rates. Illustrative estimate under the Haryana Progressive MSME & Export Promotion Policy 2026 (Gazette 114-2026/Ext, 29 Jul 2026); figures depend on the notified terms and the operational guidelines.
The assumed project
Every figure below is an assumption of this example, entered into the calculator as it stands. Change any of them in the calculator to see your own estimate.
| Land | none | Excluded from eligible capital expenditure |
|---|---|---|
| Building | none | Eligible capital expenditure |
| Plant and machinery | ₹50,00,000 | Eligible capital expenditure |
| Working capital (margin) | none | Excluded from eligible capital expenditure |
| Project cost | ₹50,00,000 | Eligible capital expenditure (fixed capital investment): ₹50,00,000 |
| Term loan | ₹35,00,000 | 10% a year, 5 years, equal monthly principal |
| Expected Net SGST paid a year | ₹2,00,000 | Mostly to registered (B2B) buyers |
| Stamp duty paid on land | none | Leased premises or no land in this example |
| Unit, sector and size | Micro | Expansion of an existing unit, manufacturing, Haryana; 5 new jobs for Haryana residents; no owner-category or exporter top-up assumed |
Incentive estimate for all four area categories
The same project in each of the four location types of clause 1(m). The category depends on the type of location, not the district; our Know Your Zone tool helps place a plot. Interest subsidy is the calculator's total over 3 years on the reducing loan balance; Net SGST is the total over 7 years.
| Head | Core | Intermediate | Sub-Prime | Prime / Focus |
|---|---|---|---|---|
| Capital Investment Subsidy (clause 4.1.1)Core: 15% (core area) of ₹50,00,000 eligible capital expenditure · Intermediate: 20% (intermediate area) of ₹50,00,000 eligible capital expenditure · Sub-Prime: 25% (sub / prime area) of ₹50,00,000 eligible capital expenditure · Prime / Focus: 30% (prime / focus area) of ₹50,00,000 eligible capital expenditure | ₹7,50,000 | ₹10,00,000 | ₹12,50,000 | ₹15,00,000 |
| Interest Subsidy, 3 years (clause 4.1.2)Core: 5% a year on the reducing loan balance for 3 years (cap ₹20,00,000/yr) · Intermediate: 6% a year on the reducing loan balance for 3 years (cap ₹20,00,000/yr) · Sub-Prime: 7% a year on the reducing loan balance for 3 years (cap ₹25,00,000/yr) · Prime / Focus: 7% a year on the reducing loan balance for 3 years (cap ₹25,00,000/yr) | ₹3,67,500 | ₹4,41,000 | ₹5,14,500 | ₹5,14,500 |
| Net SGST Reimbursement, 7 years (clause 4.1.3)Core: 20% of ₹2,00,000 Net SGST a year for 7 years · Intermediate: 40% of ₹2,00,000 Net SGST a year for 7 years · Sub-Prime: 50% of ₹2,00,000 Net SGST a year for 7 years · Prime / Focus: 60% of ₹2,00,000 Net SGST a year for 7 years | ₹2,80,000 | ₹5,60,000 | ₹7,00,000 | ₹8,40,000 |
| Stamp Duty Refund (clause 4.2.3)Not in this example (no figure entered for it). | none | none | none | none |
| Employment Generation Subsidy₹48,000 – ₹1,20,000 per eligible Haryana-local employee a year, for 10 years (clause 4.6.1). For 5 new jobs that is ₹2,40,000 – ₹6,00,000 a year if every one qualifies. Depends on each employee’s salary and category, Parivar Pehchan Patra verification and the local share of your workforce (only special-category locals count below 15%), so it is not added to the total. | not estimated | not estimated | not estimated | not estimated |
| Electricity Duty ExemptionThe 2026 MSME policy’s fiscal incentives do not include an electricity duty exemption for MSMEs; the HEEP exemption was superseded on 29 July 2026. Some sector policies (e.g. EV) have their own. | not estimated | not estimated | not estimated | not estimated |
| Heads added up (before the cap) | ₹13,97,500 | ₹20,01,000 | ₹24,64,500 | ₹28,54,500 |
| Cap: 100% of fixed capital investment (clause 3.6), taken as plant and machinery + building | ₹50,00,000 | ₹50,00,000 | ₹50,00,000 | ₹50,00,000 |
| Estimated total | ₹13,97,500 | ₹20,01,000 | ₹24,64,500 | ₹28,54,500 |
- • Expansion project: the additional fixed capital investment must be at least 50% of the existing FCI, and only new plant counts — transferred or second-hand plant is excluded.
Illustrative estimate under the Haryana Progressive MSME & Export Promotion Policy 2026 (Gazette 114-2026/Ext, 29 Jul 2026); figures depend on the notified terms and the operational guidelines. Source: Haryana Progressive MSME & Export Promotion Policy 2026 — Haryana Govt. Gazette (Extra.) No. 114-2026/Ext, 29 July 2026; policy figures last verified 19 Oct 2026. No owner-category or exporter top-up is assumed; the operational guidelines the policy promised by 29 October 2026 will settle the claim forms.
Other schemes you may stack
Named from our catalogue, open on the date this page was built, with each scheme's own ceiling as its page states it. No figure is estimated for them: each depends on the bank or on its own application. The 2026 policy bars a second capital subsidy on the same component, so a component scheme is claimed on a different cost from the capital subsidy above.
- Credit Guarantee Fund Trust for Micro and Small Enterprises
Guarantee cover on loans up to ₹10 Crore
Loan or credit guarantee: not a subsidy, sits alongside the State incentives.
- Haryana Solar Rooftop Support for MSMEs 2026
30% of eligible capital investment, up to ₹25–35 Lakh by area
Covers a specific cost of its own, with its own application.
- Haryana Energy Efficiency Promotion for MSEs 2026
25% up to ₹50 Lakh, or 40% up to ₹1 Crore by area
Covers a specific cost of its own, with its own application.
- Zero Defect Zero Effect Certification SchemeCheck status
Up to 100% of certification cost (women-owned); 80% for other micro units
Covers a specific cost of its own, with its own application.
Alternatives, not add-ons
A State policy with a capital subsidy of its own for this activity. One or the other on the same machinery and building; our expert team compares them for a specific plot and product.
- Haryana MSME Automation Scheme 2026
25% of cost, up to ₹50 Lakh – ₹1 Crore by area
A capital subsidy of its own on the same component.
Not estimated: Punjab, Rajasthan and Uttar Pradesh
The calculator is Haryana-only. Punjab and Rajasthan incentives are largely a share of State tax paid and need a different working, and Uttar Pradesh is not estimated either. Their principal policies, by name:
- Punjab Industrial and Business Development Policy 2026
20% capital subsidy up to ₹10 Crore + 75% of Net SGST; total up to 100–125% of FCI
Not estimated on this site; the eligibility checker matches it by State, sector and size.
- Rajasthan Investment Promotion Scheme 2024
75% of State tax for 10 years + 3–6% interest subvention for 7 years (MSME cap ₹5 Crore a year)
Not estimated on this site; the eligibility checker matches it by State, sector and size.
- Uttar Pradesh MSME Promotion Policy 2022
10–25% capital subsidy up to ₹4 Crore; micro units also 50% interest subsidy up to ₹25 lakh
Not estimated on this site; the eligibility checker matches it by State, sector and size.
What you need before filing
The records the Haryana Progressive MSME & Export Promotion Policy 2026 entry lists for a claim; claims are filed on the Invest Haryana (HEPC) portal.
- Udyam Registration
- GSTIN
- PAN/Aadhaar
- Project Report/DPR
- CA Certified Financials
- Machinery Quotations/Invoices
- Land/Lease Documents establishing the area category
- IEC (for export incentives)
- First sale bill/invoice evidencing Date of Commencement of Commercial Production
Questions about this blueprint
How much subsidy could a ₹50 Lakh manufacturing unit get in Haryana under the 2026 policy?
On the assumptions of this blueprint the illustrative estimate runs from ₹13,97,500 in a Core area to ₹28,54,500 in a Prime / Focus area, adding up Capital Investment Subsidy, Interest Subsidy, 3 years, Net SGST Reimbursement, 7 years. Employment Generation Subsidy and Electricity Duty Exemption are not estimated. The 100%-of-fixed-capital-investment cap (clause 3.6) does not bite in any category for this project. The figures depend on the notified terms and the operational guidelines and on the department's determination of eligible expenditure and area category.
Which area category gives the highest estimate, and how do I know mine?
Prime / Focus gives the highest estimate (₹28,54,500) and Core the lowest (₹13,97,500). The category depends on the type of location, not the district: Core is land within municipal limits, Intermediate an allotted industrial plot or land between municipal and Controlled Area limits, Sub-Prime a conforming industrial zone, HSIIDC or licensed park plot or land outside Controlled Area limits, and Prime / Focus a notified Industrial Investment Promotion Zone (clause 1(m)). Our Know Your Zone tool and the land records settle it for a specific plot.
Are land and working capital counted in the capital subsidy?
No. The capital subsidy and the fixed-capital-investment cap are worked on plant and machinery plus building, ₹50,00,000 in this example. This example has no land or working capital in the project cost, so nothing is excluded. The project cost the calculator reports is ₹50,00,000.
Can the automation support and the capital subsidy both be claimed on the same machines?
No. The 2026 policy bars claiming a second capital subsidy or similar scheme on the same component, and it names automation, solar and research equipment as examples. For the automation line a unit chooses between the Capital Investment Subsidy shown here and the MSME Automation support, whichever its area category and the operational guidelines make better. The rooftop solar plant is a different component with its own scheme, so it can sit alongside either.
Can CGTMSE or a bank loan scheme be combined with these Haryana incentives?
Yes. A credit guarantee or a loan scheme is not a subsidy, so it sits alongside the State incentives; the interest subsidy is worked out on the bank loan however it is secured. What the 2026 policy bars is a second capital subsidy on the same component, under this policy or another State scheme, and the usual central margin-money subsidies are alternatives for the same unit rather than add-ons. The schemes listed on this page as stackable are named from our catalogue without figures; each has its own application.
What is not estimated on this page?
Employment Generation Subsidy: Depends on each employee’s salary and category, Parivar Pehchan Patra verification and the local share of your workforce (only special-category locals count below 15%), so it is not added to the total. Electricity Duty Exemption: The 2026 MSME policy’s fiscal incentives do not include an electricity duty exemption for MSMEs; the HEEP exemption was superseded on 29 July 2026. Some sector policies (e.g. EV) have their own. Punjab, Rajasthan and Uttar Pradesh are not estimated either, because their incentives are worked out differently; their policy pages are linked below. Nothing here is a sanction or an approval.
Want this stack for your unit? Ask our expert team
Leave your name and mobile number. Our team calls you back within one working day (Monday to Saturday).
Your details are never sold; they are shared only as our Privacy Policy describes.
Run your own figures
Put your project into the calculator with your plot's area category, check every scheme your unit matches, or ask our expert team for a DPR quote.
More blueprints: ₹1 Cr plastic packaging unit in Haryana · ₹2 Cr textile unit in Panipat · ₹3 Cr auto components unit in Faridabad · ₹25 Lakh micro manufacturing unit in Haryana · All blueprints